MRC Under Renovation Notice

Published on 20 June 2018

MRC CONSTRUCTION.JPG

As a part of the Electronic Plan Review initiative, several floors at Miami Riverside Center will be renovated. Floor renovations will affect the Planning Department, Office of Zoning, and Building.

The Office of Zoning will relocate to the second (2nd) floor. The Planning Department will remain on the third (3rd) floor, and Building Department will remain on the fourth (4th) floor.

RENOVATION WORK WILL BEGIN ON JUNE 16, 2018, AND IS EXPECTED TO BE COMPLETED BY NOVEMBER 12, 2018.

Renovation work will be completed in multiple phases to allow for day to day operation(s) of each department to continue during this time.

PLANNING DEPARTMENT......June 16, 2018 - August 17,2018

OFFICE OF ZONING...................... July 2, 2018 - September 10, 2018

BUILDING DEPARTMENT............June 16, 2018 - November 12, 2018